Process

During the past 24 months, Martin Evans Architects and John Rowan & Partners (Planning Consultants) alongside various other specialist consultants have had ongoing discussions with London Borough of Ealing developing the scheme. Various public consultations with neighbours, local MPs and Councillors have taken place and feedback has been taken on board and implemented in the planning submission. Please find below the project timeline:

TIMELINE

MAY 2016

Site visit with SKLPC Committee and members.

JUNE 2016

Initial meeting with London Borough of Ealing planning department to discuss scope and intent.

FEBRUARY 2017

First PPA (Planning Performance Agreement) meeting with London Borough of Ealing planning department.

APRIL 2017

Meeting with Sports England.
Second PPA meeting with London Borough of Ealing planning department.

JULY 2017

Third PPA meeting with London Borough of Ealing planning department.

AUGUST 2017

Fourth PPA meeting with London Borough of Ealing planning department
Meeting with TFL (Transport for London).

OCTOBER 2017

MP’s & Councillor Exhibition on Monday 16th October
Public Exhibition on Tuesday 17th October

NOVEMBER 2018

Consultation with Harvey Road residence

JANUARY 2018

Presentation to Ruislip Residents Association

MAY 2018

Formal application submission to London Borough of Ealing